Short answer: a Gantt chart is a project plan drawn as bars on a calendar. Each row is a task, each bar runs from the task's start date to its end date, so its length is how long the task takes, and a line for today shows what should be finished by now. The data behind it is three columns: task, start, end.
The chart, part by part: What is a Gantt chart? draws its parts and shows how to read one, its kinds and the mistakes to avoid.
A task list in a spreadsheet tells you what has to happen. It does not show you what overlaps, what waits for what, or which task is already late. A Gantt chart shows all three at a glance, which is why it is still the standard picture of a project plan.
How do you read a Gantt chart?
| Part | What it tells you |
|---|---|
| A row | One task |
| The bar's left end | When the task starts |
| The bar's length | How long it takes |
| Bars side by side in time | Tasks that run at the same time |
| A diamond | A milestone: a date, not a span of work |
| The today line | Everything to its left should be done |
Read it from the today line outward. A bar that crosses the line is in progress; a bar that ends to the left of it should be finished. If it is not, that is the task to ask about.
What do dependencies show?
Many tasks wait on another: design, then build, then launch. On a Gantt chart that is a bar that starts where the one above it ends, often with a small connector between them. The value is in the chain: when "design" slips a week, you can see every bar after it slip too, and whether the launch date still holds. A delay on a task that nothing waits for matters much less.
What data do you need?
Three columns, one row per task:
| Task | Start | End |
|---|---|---|
| Research | 2026-11-02 | 2026-11-13 |
| Design | 2026-11-16 | 2026-11-27 |
| Build | 2026-11-30 | 2026-12-18 |
A duration column works instead of the end date. A team or phase column is worth adding: colour the bars by it, and the chart also shows who is busy when.
When is a Gantt chart the wrong chart?
- Hundreds of tasks. The chart turns into a wall. Filter it to one phase, or to the tasks the end date depends on.
- Work without dates. A team that pulls the next card when it has time is better served by a board.
- You only need one date. "When does it launch?" is a single number, not a chart.
How do you make one in Excel and Power BI?
| Tool | How |
|---|---|
| Excel | No built-in Gantt type: make a stacked bar chart of start and duration, then set the first series (the start) to No Fill so only the duration bars show |
| Power BI | The Gantt visual (preview) shows durations, progress and milestones on a time axis; a Gantt visual from AppSource works too |
| Tableau | The Gantt bar mark, with the start date on Columns and the duration on Size |
Where can you check this?
- Microsoft Support: Present your data in a Gantt chart in Excel
- Microsoft Learn: Overview of visualizations in Power BI, the Gantt visual (preview)
Can you see your task list as a Gantt chart right away?
Paste your task list with start and end dates into Chart Compass, say the chart should show how things flow over time, and it draws the Gantt chart with your own tasks, the today line and milestones included, next to the other charts that fit. Each one comes with its name and where to find it in Power BI, Tableau and Excel. Which chart should I use? covers the other things a chart can say.